Focus and Leverage Part 266
In this posting Bruce presents the system analysis
performed by the improvement team. And
like the last posting, Bruce asks you the readers a question at the end of this posting and we welcome
all of you to post an answer to it.
The System Analysis – More
information and Details
With the tour information in hand, it was
time for the improvement team to go back and do a more detailed system analysis and look for the
cause-effect-cause relationships at each work station and determine what the
improvement strategy should be. Let’s go
back through each process step (work station) and look for more detailed
information and clues as to what might be causing the problem.
Step 1 – The Planning
The “beloved” optimization software was an
add-on from management. Management
firmly believed the software could be used to improve efficiency and help them
reduce cost per part and save on scrap material. In isolation the software might have some
benefits for a single panel, but when subjected to the number of panels
required to complete a single project, the software did pose some drawbacks.
The foundational logic of the software was to analyze and calculate
optimization for a single panel.
However, the software did not take into account or calculate the effects
on a total project. Overall, the global
negative effects of following the software recommendations did cause some
problems!
Each project manager usually had several jobs
assigned to them to manage. At any given
time the project managers could have three (3) or four (4) jobs at various
stages of the planning or production process.
The current rules for the project managers were simple:
1) Keep everyone busy (Efficiency).
2) Release work to the floor as soon as it
was ready to go (in hopes of getting it completed on time).
3) Keep pushing the job through the system.
Step 2 – The Lay-up
The lay-up process was pretty straight
forward. The capacity of the lay-up team
(2 individuals) far exceeded the needs of the saw. This work station was able to keep up or
exceed the needs of any of the work stations including doors and drawer fronts –
plenty of capacity! The only observed
issue for lay-up was sometimes a raw material non-availability. It could happen that extreme laminate colors
had been chosen, which required a special order and could delay arrival. These kinds of things didn’t happen often,
but they could.
Step
3 – The Saw
The saw operator was following the wishes of
management by trying to extract the highest levels of efficiency that he could
from the saw. As such, the saw operator
was totally focused on maintaining a very high “efficiency” at the saw, because
he was measured to make sure the saw was always busy. The internal mantra seemed to be; “If you
don’t cut it, we can’t make it…”
Partially true, but also totally wrong!
Frequently, there were times (daily) the saw
operator would “override” the optimization software and change the cutting
sequence. Several years of experience
had taught him that the software was not always right and he had developed a
better way to do it!
In the saw operators way of thinking, and
also managements way of thinking, this was always a great opportunity to save
money, if he could manipulate the process and change things to increase
efficiency and reduce the cost per part.
In time, the operator had learned that the
highest saw efficiency happened when he changed (overrode) the software to cut
the panels differently. Because of his
experience the saw operator was able to look at the entire project cut sequence
and determine the number of boxes that were all the same size. As an example, in the case of a school
project, it was clear that all of the boxes required, in all of the classrooms basically the same size – in other words, each
classroom was the same - almost. Many
times the boxes would vary in size because of a corner unit, or the length of
wall, or some other variable but, he could still get very close in his
calculations. Besides, he would/could do
the corner units and other various box sizes at a later time. Right now efficiency was the most important
measure.
When cutting pieces for the box, the left side
and the right side are exactly the same. This could vary based on box height
requirements, but even then, they were all the same. The tops and bottoms could
be a different size depending on the width required and the sequence location (i.e.,
corner unit), but, for the most part the tops and bottoms were the same.
The saw operator reasoned that if he went
through the entire job and cut ALL the left and right sides before cutting the
tops and bottoms, he would be able maximize the efficiency of the saw by
reducing the number of times he had to change the setup and give new
instructions to make a new cut. By every
measure of efficiency the saw operator was running at maximum efficiency. The saw operator was very proud of himself
for what he could accomplish and management was also proud of him! He was highly efficient and saving the
company a lot of money – or, so they thought.
Step
4 – Edge Banding
There were two operators at the Edge Banding
machine. One operator would feed the
part into the machine and the other operator would take it out at the other end
and send it back for additional edging or put it on the pallet for transfer to
the next work station if it was finished edging.
For the Edge Banding operators it really
didn’t make much difference which part they had - the process for edge banding
was the same. The only thing that really
made a difference to them was the color of the edging or if it required wood
banding. The banding materials came in
big rolls which made changing from one color to another very easy. Change-out was
about two (2) minutes, or less.
Step
5 – The Morbidelli
The Morbidelli was operated by a single
operator. The Morbidelli work deck was
actually about 40 inches off of the floor.
The set-up of the work deck allowed for two panels to be drilled at a
time, sometimes more depending on the size.
The operator could drill either the flat
sides (for the pins to hold the shelves) or drill the side edges for the dowel
pegs. The flat side took a bit more time
because there were more holes. The edges
took less time because there were only two or three holes for the dowel pegs
depending on the size of the piece.
It is interesting to note that the cutting
sequence from the saw actually helped the Morbidelli achieve a higher
efficiency. The operator could set-up to
do all of the flat sides first and then set-up to do all the edge holes when
the tops and bottoms arrived. So, in
essence, by following the same cut sequence from the saw the Morbidelli work
station also appeared to be highly efficient.
Step
6 – The Box Press
It was at the box press that the beloved
“efficiency” model fell apart! There was,
at any given time, several pallets of inventory waiting in the holding area for
the box press. In some cases there were
pallets stacked on top of pallets (with the help of a forklift), just to better
utilize the space available.
There were two Box Press operators and they
were stuck! Considering all of the work
in process (WIP) waiting in front of their work station, they DID NOT have enough of the
right parts to build a single box! What
they usually had was ALL left sides and the right sides and the backs but, no
tops or bottoms. It wasn’t until the
first tops and bottoms had completed the other processes and started to arrive
at the box press that they could start assembly.
When the tops and bottoms did start to arrive,
it was sometimes very difficult to match the pieces for the build. The reason was, the width of the boxes had a
much higher probability of changing then the height did. At times, it was like putting all the pieces
of a puzzle on a table and trying to figure out which pieces went where. Even though most of the boxes were
essentially the same size, it usually turned into a “hunt” to find the right
pieces for assembly. This problem
existed because each piece was marked with job number and cabinet number. Even though each piece was EXACTLY the same, the operators
would spend considerable time trying to match the job numbers and cabinet
numbers!
This matching of the necessary parts also
played heavily into the slow production time of the box press. The reality was the box press operators spent
most of their time “looking” for, and not “pressing” parts. By all measures the box press operators were
very busy, but they just weren’t accomplishing the job of pressing boxes.
Step
7 – Final Assembly
The assembly crews in final assembly seemed
to have the most down time. I say crews
because there was one crew who did the drawers and another crew who did the
doors. Sometimes the hardware could be
mounted early for drawers and doors.
When the doors arrived they could have the hinges mounted on them prior
to the boxes showing up. However, taking
this early action, to mount hinges on the doors, also generated a large amount
of re-work. The correct assembly process
was to first mount the hinge to the box and then the door to the hinge. This allowed them to do the proper alignment
when the door was attached.
The door crew often assembled out of sequence
just so they would appear to be busy.
They took this action knowing full-well they would eventually have to
re-work it. But, it did meet the measure
of being busy and efficient “right now”!
Step
8 – Shipping
When the boxes arrived at shipping they were
individually wrapped in plastic. They
had several different plastic rolls on applicators that they could use and
there were, at most times, probably 3 or 4 folks in shipping area. They had the capacity to keep up with the
boxes coming from Final Assembly.
When the boxes were wrapped, the box number
was checked-off of the project list and either loaded directly to the truck or
placed in a holding area waiting for the truck to return. The primary measure of shipping was to make
sure the truck was fully loaded in order to maximize the load going to the job
site and reduce the number of times the truck had to make a trip, reducing the
fuel costs and saving money, and therefore being more efficient! A truck was rarely allowed to leave for a job
site only partially loaded, unless it was to take the last pieces required to
hopefully finish the job.
As an added note, there were complaints from
the installers at the job sites. Even
though lots of boxes were showing up at the job site(s) it consisted of only a
few boxes in each room. The installers
had some pieces of the puzzle, but not enough of the right pieces to finish the
installation.
The
System Analysis
With the collection and observation of this
additional information, the system started to reveal itself and subsequently
take on a life of its own. For the
improvement team the necessary actions started to take shape for what actions
were necessary to transform the situation.
By now, many of you might have concluded where
you think the constraint is. Based on
what you have read (and your mental list of improvements) you’ve probably deduced
which work station is slowing down the entire system. What do you think the
constraint of this system is? Where
would you focus your improvement efforts?
Why would you pick that particular location or operation?
At first blush, many people might point their
finger at the Box Press. By using
traditional system analysis techniques and protocol, i.e., looking for the
slowest operation, looking for the point where the work seems to be backed up
and the point that exhibits the highest level of work–in-process inventory, the
box press would certainly be a plausible candidate. But, is it really the problem area? If the Box Press was able to produce at a
faster rate, would the entire system get better? Maybe! Remember: The Box Press has its own set of limitations. Each box is required to stay in the press for
at least 3 minutes to set the glue! Can
the Box Press go any faster than it already does with these limitations? How?
Bob Sproull