In my last posting I told you I would tie
Goldratt’s 5 Focusing Steps into Critical Chain Project Management (CCPM) and
also provide a summary of what I’ve written on this subject. Let me refresh
your memories on Goldratt's focusing steps while simultaneously tying them
into Critical Chain Project Management:
1. Identify the system’s constraints:
For a single-project environment this simply means identifying the Critical
Chain or the longest chain of longest path of dependent tasks within a
project determines the actual duration of the project. The critical chain is
therefore the constraint. In a multi-project scenario, there is a drum resource
that limits the number of projects that an organization can manage and deliver.
This resource, more than any other controls the flow of projects and is
considered the constraint.
2. Decide how to exploit the constraint:
For a single project scenario, this simply means focusing on the critical chain
tasks to make sure that the required work is done so without unnecessary
delays. In a multi-project situation, this means that projects should be
prioritized and then staggered according to the drum resource’s capacity,
making sure it is not overloaded.
3. Subordinate everything else to the above
decision: As you might have concluded, this simply means that non-critical
chain tasks cannot and must not interfere with or delay work on the critical
chain. In order to avoid this scenario, we have strategically placed feeding
buffers to prevent delays on the critical chain. In a multi-project situations,
non-critical resources may have to wait in favor of the critical chain
resources.
4. Elevate the system’s constraint: For
single and multi-project environments, this typically means investing in
additional resources or even increasing the capacity of resources that impact
both the critical chain or project throughput. Many times this might mean
spending money or using non-critical resources to critical chain tasks.
5. Return to step 1: When one project
is completed, identify/insert the next one and proceed to step 2.
Summary of Key Points
• In a fairly recent survey (The Chaos Report)
by the Standish Group, studying nearly 10,000 IT projects across America, it
was reported that 52 % of projects ended up costing greater than 189 % of the
original budget, 31 % were cancelled and only 16 % of the projects were
completed on time and on budget. The fact is, there are many other reports from
numerous industry types, from all over the world, that all conclude the same
thing, project completion rates are abysmal!
• Ninety percent of the Project Managers
around the world are using a project management method called Critical Path
Method (CPM) and have been doing so for many years. CPM uses a “fudge
factor” to protect projects from inevitable uncertainty. That is, when
developing the project plan, durations for each individual task are estimated
by the resources responsible for executing them and then a safety factor is
added to each of the tasks by the resource responsible for completing them. In Critical
Chain Project Management (CCPM), individual tasks durations are removed and
replaced with a project buffer.
• In traditional project management (CPM)
tracking is done so by calculating the percentage of individual tasks completed
and then comparing that percentage against the due date. CCPM tracks progress
on the critical chain against buffer consumption.
• There are behavioral issues associated with
traditional project management (CPM). These issues are the Student Syndrome
(or procrastinating start of the project because of the built-in safety
buffers), Parkinson’s Law (Work expands to fill the available time), and
Multi-tasking (moving back and forth between multiple projects thus
extending the duration of all of the projects). CCPM eliminates these
behavioral issues by eliminating individual task durations, using the relay
runner scenario (i.e. passing on a task as soon as it is completed), and
staggering or pipelining the projects (i.e. delaying project starts)
• Whereas CPM completion rates are clearly
abysmal, completion rates using CCPM are excellent (i.e. typically >90%) and
the completion times are usually 40-50% faster. In addition, when comparing
scope and cost, surveys of companies using CCPM, CCPM is a far superior project
management method.
I hope you have enjoyed this series on Maximizing Profitability and that you have found it helpful. In my next series of postings, I
will be discussing a variety of subjects which will include the Theory of Constraints Parts Replenishment Model. I will demonstrate how to virtually eliminate stock-outs while reducing
your parts inventory in the neighborhood of 40-50%. In closing, if you have a specific subject you'd like me to focus on, just send me an email to ras8202@live.com.
No comments:
Post a Comment