In this posting I will continue on with Appendix
1 from Epiphanized, and we will now
discuss the concept of focus and leverage
in the context of this integration. This posting is the essence of why I named this blog Focus and Leverage.
Focus and Leverage
From what has been stated so far,
you might think we have a negative view of Lean and Six Sigma, but such is not
the case. In fact, TOC by itself cannot deliver sustainable bottom-line
improvement. But it does provide the needed global system focus, and that focus
is paramount to facilitating organizational growth. In fact, the primary reason
why Lean and Six Sigma have failed to deliver acceptable ROI is they try to
improve everything all at once, rather than focusing on the most important
leverage points. They promote improvement because they can, and not because
they must. It’s like trying to solve world hunger—it’s a tough job when you try
to do it all at once. So let us discuss leverage points and what they mean.
Leverage
The foundational concepts of TOC
can be presented in a simple, but understandable way as a reference environment.
If you understand the reference, you understand the concept. If we use a
diagram showing a simple piping system with the primary goal of delivering
water, then the reference is defined. By presenting the concept in this format,
the basic principles will be much easier to comprehend for people who have not
yet had any experience with the Theory of Constraints.
[Note: This was our original view of the piping
diagram as published in Epiphanized]
The above figure describes the piping system with different diameter pipes
connected together supporting the water flowing through this system. The water
flows from left to right from Section A through the entire length of the system
until it exits at Section G. If you were given this water system and asked what
you would do to increase the flow of water, or the throughput of water, through
this system—how would you answer the question? For most responders, the answer
would be to increase the pipe diameter of Section C since it is the choke
point, or bottleneck, or constraint of this system. If you increased the diameter
of any other pipe section, it would have absolutely no effect on the throughput
of water through this system.
If you were asked how much you would increase
the diameter of Section C—how would you answer that question? Most responders would
answer by saying that the increased diameter of the Section C pipe would be
determined by how much more water the system needed to deliver (loads on the
system). So in order to satisfy the need (demand) for more water, you must have
some type of metric for how much more water is needed (increased loads on the
system). Let’s say that you increased the diameter of the pipe in Section C to
the same diameter as the pipe in Section D. What if the measured throughput of
water out of Section G was still not enough to satisfy the new demand—what
then? The new focus for system improvement would shift to the new constraints
(the constraints have moved) which are now both Sections A and E. These two
sections become interactive with each other. The diameter of these two pipes now
becomes the new system constraint, and they need to be improved to meet the
increased demand. So how does all of this apply to the real world?
Focus
The basic principles of understanding constraints are all around
us. For example, instead of using the piping system to demonstrate the
constraint, we could have substituted an electric circuit with different sized
resistors and measured the flow of electricity through the circuit. The
resistor location with the highest resistance to electrical flow would be the
equivalent of Section C in the piping diagram. You could easily demonstrate
that the flow of electricity through that system is completely dependent upon
how much more electrical current was needed to satisfy the demand. And in order
to increase the electrical output, you need to reduce the resistance of the
resistor that was limiting the electrical flow.
The figure above is another simple visual example of the same
concept. Here we have a four-step process used to produce some kind of product
or service. If we apply the same systems thinking and ask the same
series of questions about this system, then we can effectively conclude that
Step 2, at 17 days, is the process that is limiting the output from this
system. By understanding this concept you now know where to focus your
improvement efforts. Improving any other process in this system, except for
Step 2, yields no system improvements at all. Globally, the system will
improve only when Step 2 requires less time.
In my next posting we’ll roll all of this up together to better
understand just why this integration is so very powerful. We’ll also discuss a ground-breaking study that
was run in a global electronics company that offers proof of the superiority of
TLS.
Bob Sproull
No comments:
Post a Comment