In this final posting of this extended
MRO CCPM case study, I want to demonstrate the results achieved and summarize the
important lessons learned. I hope you
have enjoyed this series and that you have learned from it. Although this was a case study on a CCPM
implementation, the lessons learned apply to virtually all improvement
initiatives.
Our initial implementation yielded
results that surprised all of us. On the
very first series of aircraft, the total cycle time for scheduled maintenance
decreased by 38% with aircraft throughput increasing by 40 %. One of the keys to our early success was
reducing the total WIP of aircraft in the process by 50%. This had a major impact on reducing our
multi-tasking of aircraft and set the stage for the other aircraft that we
would eventually convert to CCPM.
Needless to say, the leadership team was impressed with the results and
encouraged up to push on to the other airframes.
As I mentioned, we cut our WIP level by 50% in
scheduled maintenance, almost eliminating multitasking, enabling the workforce
to concentrate on getting the job done without moving on to a new
aircraft. This action translated into
early finishes thus giving more available aircraft to the students to fly each
day. It also provided flexibility for
unscheduled managers to manage their resources instead of them being managed. We focused on Buffer Management, and
investing in our people with the cycle times being virtually cut in half with a
proportional increase in throughput of aircraft through our scheduled
maintenance process. Looking back, it’s
my belief that the most important learning was that we now knew that the
constraint was the actual Critical Chain and we did everything we could to
protect it.
In addition to the tangible results we
achieved, there were also many intangible benefits realized which contributed
to our overall level of success. For
one, our production control department now had the
flexibility to control which aircraft should be launched into the scheduled
maintenance process and which ones could wait.
This allowed us to plan more effectively and virtually eliminated the
“push” mentality that had “clogged” the maintenance hangar. Our unscheduled maintenance could now better
prioritize what was urgent and what would be better left to the non-launch
hectic times of the day and week, such as the week ends. Our level of communication between shifts
accelerated upward to never-before seen levels because we now had effective
shift tie-in meetings, Because of these meetings, there was never a doubt about
where an aircraft was in the scheduled maintenance process and what work had to
be done on it. This resulted in the
virtual elimination of duplicate work being done by the on-coming shift
workers.
Before CCPM, if we would have been one aircraft short for
any reason, there would have chaos in the maintenance hangar. Prior to our CCPM implementation we had requested
more hangar bays and more parking and office space for years, but in the days
after our implementation, space was no longer a problem simply because of the
WIP reduction and the speed at which we turned aircraft through the scheduled
maintenance process. One last intangible
was the lessened impact of employee attrition.
Prior to our implementation our attrition rate was around 80% which
caused extreme difficulty getting aircraft through the process in a timely
manner. With our streamlined CCPM
processes, standard work and in-house CCPM training we were able to overcome
this obstacle quite easily. The
attrition decreased somewhat, but it was the ease of information flow between
and within shifts that helped the most.
With the CCPM software, there was no longer any doubts about what the
priorities were.
The overall results of this implementation were
amazing. In the remainder of this
posting, I want to summarize the achievements made as a result of our CCPM
implementation. For example, by
reducing the WIP by 50% on all of our different aircraft types, we were able to reduce the number of aircraft
being tied up in scheduled maintenance.
Because this DoD customer did not have to purchase additional aircraft
for school use, this WIP reduction and cycle time improvement translated into more
than $90M M in savings and cost avoidance for the customer. Because of the cycle time reduction and
increased throughput by an average of 40+ %, this effect translated into the
equivalent of additional aircraft being created. Needless to say, the customer was very happy
with this effect because there was no longer a need to purchase additional
aircraft to accommodate the flight school..
Because of the WIP reduction, we were also
able to reduce the combined space requirements in two of the aircraft hangars
by over 18,000 square feet. There had
been plans to increase the size of hangars at these two airfields, but this
expense was no longer needed resulting in over $2M in cost avoidance.
Because of the reduction of WIP on another helicopter
airframe, the equivalent of giving back two aircraft for immediate school use
resulted in approximately $60M in cost avoidance and savings for this DoD customer. Because of the reduction in scheduled
maintenance cycle time on this aircraft by an average of 47%, like the other
aircraft significant $ savings were realized.
Finally, the CCPM implementation resulted in totally
eliminating the need to outsource aircraft for scheduled maintenance in 2009
and 2010. To put that in perspective, in
2008, approximately 19% of two of the aircraft types had been outsourced and by
eliminating this need, significant dollar savings were realized.
Before closing, I want to summarize what I feel
were the keys to success in this CCPM implementation and then finish with our lessons learned. In no particular order of
importance, the keys to our success were:
- The creation of a “core team” comprised mostly of the true subject matter experts (SME’s). The SME’s are the actual people doing the work which in our case study they were the mechanics, avionics tech’s, QA inspectors, logistic’s personnel, etc. They must be permitted to define the new methodology without reservation and interruption by the leadership of the organization.
- Top Management and leadership must be committed to the success of the CCPM implementation. They must let go of the command and control mentality that many leadership teams exhibit. Regardless of what the leadership team thinks, they truly are not the experts when it comes to doing the work.
- In addition to leadership’s commitment, they must also actively participate in the implementation of CCPM. Leadership must be ready at all times, to remove any barriers that get in the way of the SME’s.
- The establishment of a robust and active problem resolution process is critical to the success of any CCM implementation. No longer can symptoms of a problem be treated, but rather root cause analysis must be the order of the day. If only the symptoms of the true root cause are treated, the problems will resurface time and time again.
- One of the keys to for a CCPM implementation is the subordination of all other processes to the success of CCPM. This has to be the priority focus.
- he CCPM software is the vehicle for prioritizing the work to be done every day. These priorities are color-coded in their order of importance with all “reds” being the top priority, followed by “yellows” and then “greens.” The SME’s can no longer pick and choose what to work on or the implementation will not succeed.
- Finally,
the performance measures must be changed to reflect the new way of managing
projects. The ratio of % buffer consumed
to % critical chain complete is a simple, yet very effective way for leadership
to monitor project status. In addition,
the fever charts should be reviewed by leadership and everyone else and any
place where buffer consumption is heading due North should become the top
priority for everyone concerned. For if
the reason for the excessive burn rate of the project buffer is not corrected,
the project is guaranteed to be late.
There
may be other keys to success, but these are some of the more important ones
that we observed in our implementation. CCPM
is clearly much more effective than CPM in terms of project completion rates.
I'd like to finish this series by discussing some of the more important lessons learned from this CCPM implementation.
- First, we learned that if you want a project plan to work, make sure that the true subject matter experts are the ones to develop it. It doesn't matter if it's a software development process or, like ours, an MRO project. If the true SME's aren't used to develop it, it will fail!
- We learned that attempting to measure local efficiencies in the process will take you in the wrong direction. It's important to understand that excess capacity is truly not a bad thing. In fact, having excess capacity at various parts of the process helps to improve your flexibility.
- Leadership's role must become one of support rather than directing the team's activities. There's no room for the old "command and control management style." Leadership's involvement must include being available to remove barriers when the workers need their help.
- Being able to sustain your improvements is, by far and away, the most difficult behavior to achieve. The natural tendency for the work crews at this MRO site is to fall back to their old ways and habits. You must constantly reinforce this new way. The good news is.....this new way is much less stressful.
Bob
Sproull
No comments:
Post a Comment