The Robust Supply System
One of the primary operating functions of the supply-chain system
is to build and hold inventory at the lowest possible distribution level. This
assumption is both correct and incorrect. The correct inventory should be held
at the POU location, but not based on minimum/maximum amounts. Instead, the
necessary inventory should be based on the vendor lead times to replenish and
maintain sufficient inventory to buffer the variations that exist in lead
time. The TOC Distribution and Replenishment Model is a robust parts replenishment
system that allows the user to be proactive in managing the supply-chain
system. It’s also a system based on usage, either daily or weekly, but not the
minimum amount. Some parts/inventory will require much more vigilance in
day-to-day management. Table 3 defines
the suggested criteria required to implement a TOC Distribution and
Replenishment Model in a supply-chain system.
Table 3
Criteria
needed for the TOC Distribution and Replenish Model
1. The system reorder amount needs to be based on daily or
weekly usage
and part lead-time to replenish.
|
2. The system needs to allow for
multiple replenish orders, if required. |
3. Orders are triggered based on buffer
requirements, with possibly daily actions, as required. |
4. ALL parts/inventory needs to be available
when needed. |
5. Parts inventory
held at a higher level, preferably at Central Supply locations or directly
from the supplier /vendor. |
6. Part buffer determined by usage rate and replenish
supplier/vendor lead-time. Baseline
buffer should be equal to1.5. If
lead-time is 1 week, buffer is set at 1.5 weeks. Adjust, as required, based on historical
data. |
The TOC
Distribution and Replenishment Model argues that the majority of the
inventory should be held at a higher level in the distribution system (supply
chain) and not at the lowest level. It is still important to keep what is
needed at the lowest levels, but don’t try to hold the total inventory at that
location. The TOC model is based on the characteristics of a “V” plant
distribution model. The “V” plant model assumes that distribution is fractal
from a single location—in this case either a central supply location or a
supplier/vendor location (the base of the “V”)—and (see Figure 1) distribution
is made to different locations (the arms of the “V”). The “V” plant concept is
not unlike any supply-chain distribution methodology. However, using a “V”
plant method has some negative consequences, especially when working under the
minimum/maximum rules (as shown in Figure 2.) If one is not careful to
understand these consequences, the sys-tem can suffer dramatically. One of the
major negative consequences of “V” distribution is distributing items too early
and sending them down the wrong path to the wrong location. In other words,
inventory is released too early and possibly to the wrong destination. This is
especially likely to when the same type of inventory or part is used in several
locations.
Has it ever happened that at one location you
have a stock-out situation, and one of the rapid response criteria for finding
the part is to check another production line within a company or call back to
the distribution center? If this is the case, then parts/inventory distribution
has taken place too early in the system. Sometimes, it’s not that the system
does not have the right parts/inventory; it’s just that they are in the wrong
location. Distribution from a higher level in the chain has been completed too
quickly. The TOC Distribution and Replenishment Model also argues that the use
of minimum/maximum amounts should be abolished. In-stead the inventory should
be monitored based on daily or weekly us-age, with replenishment occurring at a
minimum weekly and possibly daily for highly used items. The end result of
these actions will be sufficient inventory in the right location at the right
time—with zero or minimal stock-outs—to support production activity. Instead of
using the minimum amount to trigger the reorder process, it should be triggered
by daily usage and vendor lead time to replenish. As an example, suppose we
apply the TOC Distribution and Replenishment Model rules to exactly the same
criteria discussed earlier. We will use the same part simulation, and the same
period of time, with the same usage numbers. The difference will be in this
simulation we will change the rules to fit the TOC Distribution and
Replenishment Model—based on usage amount and vendor lead time rather than minimum
and maximum amount.
Table
4
Simulated
Data applied to TOC Distribution and Replenish Model
Week #
|
Current Inventory
|
Actual Items Used
|
Weeks end inventory
|
Items added (Replenish)
|
WK 1
|
90
|
10
|
80
| |
WK 2
|
80
|
15
|
65
| |
WK 3
|
65
|
15
|
50
| |
WK 4
|
50
|
15
|
35
|
10
|
WK 5
|
45
|
5
|
40
|
15
|
WK 6
|
55
|
15
|
40
|
15
|
WK 7
|
55
|
15
|
40
|
15
|
WK 8
|
55
|
10
|
45
|
5
|
WK 9
|
50
|
10
|
40
|
15
|
WK 10
|
55
|
15
|
40
|
15
|
WK 11
|
55
|
15
|
40
|
10
|
WK 12
|
50
|
15
|
35
|
10
|
WK 13
|
45
|
8
|
37
|
15
|
WK 14
|
52
|
12
|
40
|
15
|
WK 15
|
55
|
10
|
45
|
15
|
WK 16
|
60
|
10
|
50
|
8
|
WK 16
|
58
|
5
|
53
|
12
|
WK 18
|
65
|
10
|
55
|
10
|
WK 19
|
65
|
10
|
55
|
10
|
WK 20
|
65
|
10
|
55
|
5
|
WK 21
|
60
|
15
|
45
|
10
|
WK 22
|
55
|
18
|
37
|
10
|
WK 23
|
47
|
15
|
32
|
10
|
WK 24
|
42
|
12
|
30
|
15
|
WK 25
|
45
|
10
|
35
|
18
|
WK 26
|
53
|
15
|
38
|
15
|
The Table 4 data also assumes that no parts inventory is held at the next higher level and that the parts replenishment has to come from the vendor and consumes the allotted vendor lead-time. However, if the parts/inventory were held at higher level in the distribution chain (Central Supply or a distribution point), Table 4 presents the simulated data for a random reorder scenario using the TOC Distribution and Replenishment Model. In this example we will assume the following:
- Maximum level is ninety items. (This is the start point for the current inventory.)
- There is no minimum reorder point; instead reorder is based on usage and vendor lead time.
- Lead time to replenish is still four weeks.
- Average usage of the part is about ten per week.
The Table 4 data also assumes that no parts
inventory is held at the next higher level and that the parts replenishment has
to come from the vendor and consumes the allotted vendor lead time. However, if
the parts/inventory were held at a higher level in the distribution chain
(central supply or a distribution point), and replenish happened daily and/or
weekly, then the total inventory required could go even lower than the data
suggests. This could happen because distribution is completed weekly rather than
waiting the full four weeks for delivery. The part usage rates are exactly the
same as the previous run and the starting inventory is equal to ninety parts.
This also assumes we have a weekly parts/inventory replenish after the initial
four weeks of lead time has expired. In other words, every week we have
delivered what was ordered four weeks ago. In the TOC scenario the reorder
point is at the end of each week based on usage. The total number of parts used
is the same number of parts that should be reordered.
Figure 4 shows the effects of using
the TOC Distribution and Replenishment Model. What is most notable is that
total inventory required through time has decreased from ninety items to
approximately forty-two items. In essence, the required inventory has been required through time has decreased from ninety items to
approximately forty-two items. In essence, the required inventory has been cut
in half. Also notable is the fact that there are no stock-out situations
present.
When
the TOC Distribution and Replenishment Model is used to manage the supply chain
there is always sufficient parts inventory to continue production work. The
total inventory is also much more stable, through time, without the large gaps
and gyrations from zero inventories available to maximum inventory as noted on
the first run (Figure 4) using the minimum/maximum system.
In my last posting in this 6-part series on Part's Replenishment Systems, we'll look at a very ingenious and relevant way that Bruce has chosen to present an example of how the TOC Parts Replenishment System is intended to work.
Bob Sproull
No comments:
Post a Comment