Several years ago I was working for a contractor to
one of the Department of Defense military entities.
This contractor was responsible for the Maintenance, Repair and Overhaul
(MRO) on a fleet of helicopters used to train future DoD Aviators. When I arrived at this military complex there was an
active Lean Six Sigma initiative in place with regular progress updates taking
place. The contractor was focused primarily on cost
reduction to enhance their profitability using traditional cost accounting techniques to calculate hard
savings. And each month they had to report their cost savings to their customer. The contractor’s on-time
delivery rate was not as good as it should have been and to make matters worse, the contractor was using exorbitant
amounts of overtime to complete the maintenance, repair and overhaul on these
aircraft. But even with overtime, delivery
rates were not acceptable.
There were five airfields at this military complex with multiple
types of rotary wing aircraft and in an effort to complete more aircraft
through their scheduled maintenance process, the contractor was even outsourcing several helicopter for scheduled maintenance in an attempt to improve the availability pool for their customer. But even with this outsourcing, the contractor was not meeting their contractual requirements and for each aircraft under the contracted amount, the DoD customer imposed a stiff financial penalty.
There were also numerous back shops which were
responsible for maintaining, overhauling and repairing various parts to support the contractor’s scheduled
and unscheduled maintenance efforts. In
this next series of postings, I want to present what this team did to turn this
effort around to produce never-before-seen-levels of on-time delivery to this DoD customer at this military complext. Because of
the sensitive nature of what I am going to present, I will be using coded data
such as percentage improvements rather than actual cycle time numbers. It seems like only yesterday that this
amazing turn-around took place.
When I arrived at this installation the maintenance
functions were using simple SOP’s aimed at identifying the sequence of activities that
had to be completed in order to complete their scheduled maintenance process on the
various types of helicopters. It wasn’t
a true project management effort, but they did use a project management
software loosely based on the popular Critical Path Method (CPM). (Note: On several occasions, I have shared the
problems associated with this type of project management method, so check out
my index of postings if you’d like to learn more about these issues). Because of the length of time required to
complete the scheduled maintenance on each aircraft in the system (i.e. over a month for each aircraft), each aircraft was
treated as a separate project. As I
mentioned earlier, the on-time delivery rate of aircraft through their scheduled maintenance area
was not good and this contractor was paying the price for late deliveries by
way of money penalties assessed by the customer.
Also, when I arrived at this facility, the contractor's Continuous
Improvement Group had only 2 Black Belts, 1 Master Black Belt, and 1 Lean Assistant to
support the 5 airfields, the different helicopter fleets, and the many back
shops. I originally started there as a subcontractor, but when my contract ran out, I was promoted to the Manager of this CI Group. The members of this group were well-schooled in Lean Six Sigma. What I brought to this facility was something new....a working knowledge of the Theory of Constraints (TOC) which was a totally new concept for this facility. One of the first lessons I had to
teach everyone was that every business has key leverage points and that in order to achieve significant improvement, we must focus
our improvement efforts on them. In order to significantly improve flow, it was necessary to optimize the cycle time of the process in question. Of course the leverage point is the system
constraint, so by identifying it and focusing our improvement resources there,
we achieved the optimum return on our improvement resources.
I also had to teach everyone that constraints were not always physical in nature and that many times the constraints were actual policies and procedures put in place which were frequently the result of a spontaneous reaction to a problem identified by the DoD customer. And the further I got into it, the more I realized how important this lesson was because there were many, many spontaneous actions put in place to appease the customer.
Neither the contractor or the customer had never used the Theory of Constraints (TOC) before, so I had to develop presentations to, in effect, educate the masses. This education started at the top of both the contractor and customer organizations because without leadership’s active support, our improvement initiative would most surely fail. I started the journey of educating everyone on TOC by using the following simple drawing of an imaginary process.
I also had to teach everyone that constraints were not always physical in nature and that many times the constraints were actual policies and procedures put in place which were frequently the result of a spontaneous reaction to a problem identified by the DoD customer. And the further I got into it, the more I realized how important this lesson was because there were many, many spontaneous actions put in place to appease the customer.
Neither the contractor or the customer had never used the Theory of Constraints (TOC) before, so I had to develop presentations to, in effect, educate the masses. This education started at the top of both the contractor and customer organizations because without leadership’s active support, our improvement initiative would most surely fail. I started the journey of educating everyone on TOC by using the following simple drawing of an imaginary process.
\
I started the training, by simply asking the
audience the following question: Assuming
you are on day 1 of this process, how many days would it take to process the
1st part through all four steps? That is, what is the throughput rate for the first part? The audience was able to correctly answer this
question by adding the individual processing times in all four steps to get 1 part in 25 days. I then asked them this question: Now, the process has been up and running for
several weeks (i.e. the process is full).
What is the throughput rate of this
process now? As I recall, initially
nobody was able to answer this second question correctly. The correct answer is 1 part every 17 days or
the time it takes the constraint to complete its work on the part. This was a totally new concept for everyone and it made everyone see why I wanted to focus improvements there first.
I then asked them these three questions: What if someone had an idea to reduce Step 3
from 5 days to 3 days? Would the
throughput change? Or how about Step 4
if someone had an idea to cut the days in half from 2 to 1? The majority of the audience thought it would
be a good idea to spend time reducing both steps. I explained to the audience that if we wanted
to improve the throughput of the process, we must first focus our improvement
resources on Step 2 because it controls the throughput of this process. I also explained that by using Goldratt’s 5
Focusing Steps we would identify Step 2 as our leverage point and exploit it by
applying Lean and Six Sigma to reduce waste and variation in Step 2 only. We would then subordinate everything else to
Step 2, meaning that the other steps should not "out-run" Step 2. And if we still didn’t have
enough throughput, we would elevate Step 2 until we did which typically means spending some money. If the constraint moved, we would simply move
our improvement resources to it. This approach was all new to
the leadership team, but most of them thought it made perfect sense.
I can’t tell you how important it was for
the leadership team to both understand and embrace this method before we could
move on. Without the active support of a
company’s leadership team, any improvement effort will wither on the vine or
never move forward. It's also extremely important to actively involve the shop floor workers in any improvement process which is exactly what we did. In a future posting I'll discuss my version of "involvement" of the shop floor workers.
The immediate change we made to the
existing continuous improvement effort was to combine Lean, Six Sigma and the
Theory of Constraints as depicted in the following figure. This was the actual drawing we presented to
the leadership team which was depicted as planets orbiting in a solar
system, but each interconnected with the others. In retrospect, the arrows
progressing around planet Six Sigma are going in the opposite direction that
they should be, but I can honestly tell you that I or nobody else noticed it
back then. (Note: You will notice that in planet TOC there is a
blue rectangle. I placed it there to
cover the name of a software we used to “right” the ship, so to speak, in terms
of the project management we used to effectuate our turn-around).
Another important learning for the contractor’s leadership
team was that sometimes the constraint is located outside of our process, so I
had to explain how we identified it and what we do next? I explained that by using either a Value Stream
Map or a Process Map, we could identify the current and potential future constraints and either
immediately perform a Rapid Improvement Event (RIE) or poise our improvement
resources so that if and when the potential constraint became a constraint, we
would be ready to attack it. When this
constraint is broken, we moved to the next one and the cycle of improvement
continues.
For those of you new to my blog, what I’m referring to
is Dr. Goldratt's Theory of Constraints 5 focusing steps which are:
- Identify the system constraint (i.e. the bottleneck)
- Decide how to exploit the system constraint (make the most out of)
- Subordinate everything else to the system constraint (run all process steps at the same pace as the constraint)I
- f necessary, elevate the system constraint (In the first 3 steps, you shouldn’t be spending money, but if you still don’t have enough capacity, you might have to spend some) Return to step 1, but don’t let inertia create a new system constraint (inertia in this case means don’t become complacent)
- Return to step 1, but don't let inertia create a new system constraint
In my next posting, I’ll dive deeper
into how things were improved at this contractor’s work place that resulted in
significant gains in the scheduled maintenance of helicopters at Fort Rucker.
Bob Sproull
2 comments:
The diagram looks very familiar.
Since you created them John, I guess you would recognize them. Stay tuned on this series and you'll probably recognize other things. Those truly were the "good old days,"
Post a Comment